west point
Engineer
IMO the only way to get more V-2s is to transfer the CAF facility to Siemens along with all builders drawings.
The Superliners are going to have to be replaced sometime in the next decade.
They just finished a run of Viewliner IIs whereas nobody could get past the crash test phase of a bi-level car.
Why do you think another run of Viewliners is so unlikely?
Because it's probably cheaper to just have a company like Siemens build long-distance cars based on their off-the-shelf Venture platform than having them take the 40 year old Viewliner design and update it. Certainly, neither Amtrak nor CAF want to work together on anything for the foreseeable future.
The biggest problem is that CAF seems to be extremely slow in getting VLIIs out - I don't think all the sleepers have been delivered yet and we're already at least 5 years past the promised last-delivered date when the contract was signed. If we want enough cars to replace the Superliner fleet within the next 50 years, it'll be best to find an off-the-shelf rail car (even if it's single level) and use that instead of trying to build from scratch (even with a known design.)
Siemens already has something that can be worked with:I recall reading somewhere the Seimens is currently only providing a replacement for coaches, not anything else. That said, no idea if they have something of the like up their sleeve.
The last two sleepers were delivered August 24thThe biggest problem is that CAF seems to be extremely slow in getting VLIIs out - I don't think all the sleepers have been delivered yet and we're already at least 5 years past the promised last-delivered date when the contract was signed. If we want enough cars to replace the Superliner fleet within the next 50 years, it'll be best to find an off-the-shelf rail car (even if it's single level) and use that instead of trying to build from scratch (even with a known design.)
The last two sleepers were delivered August 24th
I've heard that the LSL will be getting them soonI know this probably has been mentioned, but is there any plan at all to deploy the remaining 15 or so sleepers?
There are also issues of the additional required cars fitting stations that even now require multiple stops by a Superliner (one for coach passengers, one for sleeper passengers and possibly one for baggage).Given that the next generation of Superliners officially got cancelled, the only thing preventing the use of Viewliner IIs are the lower platforms in the places the Superliners roam.
Increasing number of trains would drastically increase costs. The practical answer to short platforms is to build longer platforms. This should be an Amtrak basic long term policy. That it is a problem doesn't seem rational, as for the most part the Amtrak trains are shorter than those run on these routes in the past. Even if the platform itself is no longer there, the ground to support it should still be there.There are also issues of the additional required cars fitting stations that even now require multiple stops by a Superliner (one for coach passengers, one for sleeper passengers and possibly one for baggage).
Now, if instead, they ran a separate sleeper train from coach train or two combo trains a day on each route, that would be different.
The issue is that Amtrak doesn't own a lot of the stations. However, I'd point out that in quite a few cases, two spots should still cut it if you're not doing checked luggage at the station in question: Needing more than that is (arguably) down to the on-board staff not managing seat allocations properly (or, perhaps, being subject to a computer being stupid about it)...a lot of the stations in question only manage a few thousand passengers per year.Increasing number of trains would drastically increase costs. The practical answer to short platforms is to build longer platforms. This should be an Amtrak basic long term policy. That it is a problem doesn't seem rational, as for the most part the Amtrak trains are shorter than those run on these routes in the past. Even if the platform itself is no longer there, the ground to support it should still be there.
The NEC wasn't subject to a "short-sighted" design. Penn Station was built in 1910 and planning began in 1901. The first bilevel cars in the US weren't deployed until 1950 (commuter cars on the CB&Q). The first long-haul cars were, of course, the Santa Fe Hi-Levels. Many other "choke points" on the NEC long pre-date Penn Station (e.g. the Baltimore tunnels, which date back to 1871). Expecting the planners and builders of the NEC to "future-proof" their designs by 40-80 years is just absurd.The entire northeast clearance problem is based on shortsightedness in the original design. First and foremost in building any transportation structure is, DON"T SHRINK WRAP THE EQUIPMENT!!!!! This message does not see to have even gotten to the rebuilds and "improvements" under construction in the Northeast. I put improvements in quotations because if you do not improve your clearances you are not really doing the whole improvement job.
It would arguably simply be cheaper to extend at least two tracks' worth of platforms (either one or two platforms) at all Amtrak-served stations to accommodate 16-car trains (vs the current tendency to "cap out" around 10-12) with level boarding than it would to fix the clearance issues to accommodate Superliner-specced equipment.
I'd also point out that depending on the number of stations involved, absorbing a few "double spots" isn't the end of the world for the LD trains while after you cross a point, shorter-distance trains almost assuredly make sense to add frequencies to instead. The NEC is somewhat unique in this respect (or at least, was unique pre-pandemic) insofar as the raw amount of traffic (particularly at peak hours) stressed capacity.An awful lot of the platforms from New York to Miami were originally long enough for 16-car trains already, and so are a bunch of the older stations on the Water Level Route (LSL). They just need new concrete poured. There are a few problem locations like Syracuse (where the original station had the tracks replaced with an expressway, forcing the new station to be in a disadvantageous location) but not many, and even Syracuse can have the platforms extended, physically speaking.
A country such as India already has high catenaries for freight and tall passenger cars and can get them at low prices. With that in mind, getting high catenaries should not be that much of an issue in the east. In the west, I can see the concerns as to why but besides tunneling high catenaries in the east are the least of worries in price.It's not just the North River and East River tunnels which would have to be enlarged. There are probably many more places and overpasses where the catenary would have to be raised.
You're talking big bucks. Where would the money come from?
jb
India has high catenary only for double stack on very select routes known as Dedicated Freight Corridors, and some associate regular main lines e.g. Delhi Cantt. to just outside of Rewari. None of it is for high passenger cars of which India has none. There are no major passenger stations with high catenary.A country such as India already has high catenaries for freight and tall passenger cars and can get them at low prices. With that in mind, getting high catenaries should not be that much of an issue in the east. In the west, I can see the concerns as to why but besides tunneling high catenaries in the east are the least of worries in price.
Enter your email address to join: