I think they do have an "advantage" in that traffic here is very bad, and the RTO push (Miami-Dade County is starting to require it soon) is making it worse.
I think they got a mulligan on the first one, if only because the initial shutdown happened alongside everything else shutting down (even Disney!). However, I agree that the second squeeze will be harder to recover from - per their reports at the time, Brightline basically had a *commuter train* covering its operating costs, but they were also shaking out extra capacity at the time (e.g. there was an extra rush hour round-trip) that can't be done with all of the sets now spoken for.Thanks for the excellent and detailed analysis.
I think it's always difficult to constrict ridership and then want to rebuild it. Customers tend to be loyal and will often build their lifestyle around being able to use the train, and in doing so bank on the railroad upholding their side of the bargain by maintaining the service. Brightline have struggled over this twice. the first time was with their total and prolonged shutdown over Covid (at a time that Amtrak delivered a reduced but still essential service) and this in Florida, a state that was supposedly more lenient than many other states on restrictions from a legal perspective. And then a second time by constricting out short haul riders in favor of long haul ones. So basically now they are trying to re-start a third time. Passenger confidence or loyalty is not a commodity that can be taken for granted.
So the expectation is that they will get those 20 additional coaches delivered during the next 3 months (Q2)? Seems to be a quickly approaching deadline but hopefully they can hit it.If my tally is correct they now have 10 sets of two locomotives and five coaches, plus one spare locomotive, with a further 20 coaches on order presumably to be delivered in two batches of 10.
The January report said the following:So the expectation is that they will get those 20 additional coaches delivered during the next 3 months (Q2)? Seems to be a quickly approaching deadline but hopefully they can hit it.
To address this capacity limitation, we have on order 10 more additional Smart class passenger cars and another 10 Premium class cars to be delivered in batches that will allow us to operate seven-car long trains in mid-2025, with a maximum capacity of 450 seats. In December 2024, our second group of new passenger cars shipped from the Siemens facility in Sacramento, California. The cars, configured as Smart class passenger cars, were placed into service as of early January.
Something doesn't add up here.The first 5 cars were delivered in late September and began entering service in October, right before Milton. Afterwards, Brightline temporarily cannibalized cars off of 2 sets to create 9 5-car sets, with 1 set having 2 premium cars, and operated with 2 fewer round trips. The second 5 cars were delivered in December and began entering service in late December and they returned to the regular schedule, I believe, on January 6th. As far as I know, the third round of 5 cars has not been delivered yet.
I should have clarified, they took one red car and two orange cars out of their respective sets and combined the remaining cars into the 9th set. Seems odd but it must have been more convenient.Something doesn't add up here.
I assume one set must have been cannibalized, not two. This would have provided 4 cars (one of which Premium) with which to extend the remaining four 4 cars sets to 5 cars each.