  1. GDRRiley

    San Clemente landslide affects Pacific Surfliner 1/24/24

    they likely cost 5-10M a month, adding more walls is the near term fix and likely going to cost 50m to protect the most likely slide spots. Also needs CCC approval the long term fix is a bypass along I-5 which mattering on how much is tunneled would likely be 5-10B.
  2. GDRRiley

    California HSR

    They most likely are going to use the Siemens Velaro Nova wide which is 3300mm wide. that would also mean 7 93ft cars vs 8 85ft cars They've long ago decided trains will be ~50in floor height
  3. GDRRiley

    Brightline Trains West!

    ETCS is the signaling side of ERTMS. it uses RFID ballasts as the primary means of location tracking. The train then tells the signaling system where it is. This only applies to L2 the version that will be used by brightline west and CAHSR. L1 is a overlay on top of a legacy system while L3...
  4. GDRRiley

    San Clemente landslide affects Pacific Surfliner 1/24/24

    this was done 100+ years ago We started the plan to move it 20 years ago but it never advanced out of some early concepts Given the scale of the issue it should be reopen in 2-3 months maybe 1 month if they start working 24/7 instead of the 12/5 they were doing last time
  5. GDRRiley

    Winter Storm 2024 cancellations

    I'm going to link this video showing the challenges 3 years ago of running the empire builder. BNSF for whatever reason is using electric heaters in an area known for losing power and had to bring in generators for signals and crossings. Western Pacific on their rural sections for decades...
  6. GDRRiley

    Superliner trains' removal and restoration of cars (2022-2023)

    its still not much better, amtrak has like 40 superliners they need to get in service this year including 20 transition dorms
  7. GDRRiley

    Surfliner San Diego yard delayed

    LOSSAN did not have a written agreement with BNSF nor did BNSF staff who then left write it down. BNSF then agreed to let others use the property so lossan is out of a site. Delaying the project as they now have to go back to site selection. There are no sites nearby so they likely have to go...
  8. GDRRiley

    Long Distance (LD) fleet replacement discussion (2022 - 2024Q1)

    the standard height at this point is looking like 24in platforms with 23-25in floor railcars or the ~48in standard the first is what europe low floor stock like KISS, FLIRTs ect use and with the new US regs it makes sense that shorter regional and intercity trips will grab those multiple units
  9. GDRRiley

    Winter Park (Colorado) Express is back

    That sounds like UP, why keep 1500ft of track maintained Shame amtrak can't get 1-2 more coaches for the train seems very popular
  10. GDRRiley

    California HSR

    I also somehow forgot that LA-Anaheim/Irvine will be shared with freight including the LA-Fullerton section of the BNSF southern transcon
  11. GDRRiley

    California HSR

    There has been talk of reaching Mojave but then the line leaves LA county so then Kern and or the city would need to fund operations
  12. GDRRiley

    California HSR

    No the FRA crash standards allow eruo spec trains with some minor changes as FRA T3. T3 are allowed to run with conventional (T1), conventional alternative (euro mainline spec T1alt), or T2 (Acela Express) at upto 125mph with the NEC having a waver for 160mph The American Pionner 220 has some...
  13. GDRRiley

    California HSR

    it would have just been from Bakersfield to Palmdale as Palmdale to LA is already owned by LA metro and with some work can get much faster. BNSF was willing to let the state run at 90mph but the state decided to not fund the upgrades needed as it was part of a larger goal to try and get running...
  14. GDRRiley

    Long Distance (LD) fleet replacement discussion (2022 - 2024Q1)

    alstom last built cars mostly based on the design in 2005, it can be done the question is why would you do that when theres a lot of shortcomings
  15. GDRRiley

    Long Distance (LD) fleet replacement discussion (2022 - 2024Q1)

    the lack of watching over Alstom is why there are dozens of trains made and some entire car types without the units being certified for service
  16. GDRRiley

    Long Distance (LD) fleet replacement discussion (2022 - 2024Q1)

    I doubt Amtrak would get their new fleet without MU controls on all cars. at this point at least 25% of superliners have had it added and the cost savings is so minor
  17. GDRRiley

    Long Distance (LD) fleet replacement discussion (2022 - 2024Q1)

    Separately it seems, I wouldn't be surprised if it was build us viewliners and or venture cars for eastern LD unlikely they will top and tail, the locos stacked on the front are setup so that if 1 dies or can't lead its easy enough to have the other one do so. Back in the steam heat days and...
  18. GDRRiley

    Management issues of State funded services

    All California services have track access and priority based on paying for it. The state has millions a year up for grabs if BNSF and UP can keep trains above 85% OTP with most of the money not coming in till they hit 95%. This isn't overall OTP but what the freight railroads can affect. We...
  19. GDRRiley

    Amtrak California extension to Reno possible?

    This report looks at station changes, layover facilities ect. it doesn't address possible capacity issues which will be really fun to deal with given a large single track tunnel near the top.
  20. GDRRiley

    BART derailment 1/1/24

    Train was in manual mode after the operator had to throw switches manually because of a signaling issue Normal Yellow line service today following overnight repairs and inspections | Bay Area Rapid Transit
Back