New Acela Update
Approval for Stage 1 Qualification Testing (QTP2) was received from the FRA in December 2023. Testing began the week of January 8, 2024, and is expected to continue through the end of March 2024
• Serial Trainsets TS03, TS04 and TS05 were returned to Hornell and replaced with TS08, TS09 and TS10 in PCY. This exchange reduced the number of outstanding modifications in the field (FMIs)
• TS11 is targeted for shipment from Hornell in February 2024 and will be used for training (e.g., mechanical QMP, Engineer/Conductor, OBS etc.)
• 6 Trainsets to be commissioned before launch of revenue service
• Start of revenue service, targeted for late CY2024