They may be waiting for the Devils Lake sub to reopen but I shouldn't think it would take 6 months more like 6 days. Here's what the BNSF website said about "Proactive Measures":http://www.grandfork...icle/id/209481/
"several more days"...
They're definitely waiting for the Devils Lake line to reopen before restarting service. I hope that Amtrak will be willing to use the KO detour during the 6+ months required to raise the track near Devils Lake. If not, that will be a very long service suspension
Mark
Creston subdivision - BNSF has raised two mainline tracks up to 8 feet in order to remain in service. Levees have been built to 6 feet above top of rail along both sides of the track and portions of the roadbed have been armored with rip rap (boulder-size rock.) BNSF has filled 160,000 sandbags to be used on the levees if needed.
Glasgow subdivision - BNSF has raised track a total of 5 feet in order to remain in service. Over 300 cars of ballast and rip rap were used to raise and fortify the track.
This didn't take months to complete as the Missouri came up almost as fast as the Souris/Mouse river. Still hoping that the EB is running on the 20th as that means it will probably be running on our start date of the 23rd of this month.
There is also something in the works that sounds like they (BNSF and Amtrak) plan to totally rebuild the tracks along this flood prone stretch.