2 of the remaining 3 trainsets are to be delivered to Orlando in July or August. Last trainset delivered by the end of 2022.
but when will they be available for service?

typically when new trains are delivered they still require a fair deal of testing and detail adjustments, plus various sign-offs.

It's not really like buying a new car that you can then drive around in from day one.
 
A RR does notjust lay ballast then tamp surface and forget it. Trains have to run over it and then any imprefections need surfacing again. The FEC portion can at least have heavy FEC freights but Cocoa to ORL is different.
 
Tourists would have to pay the gas tax same as residents. Also tourists would have to pay tolls, and I don't know about Florida, but our electronic tolling system provides discounts for in-state residents.
Only those who drive in or rent a car. They all pay sales tax on meals, hotels, etc. The county mayor estimates 51% of sales taxes are paid by tourists.

Everyone pays the same tolls in FL if they have a transponder, whether local or from out of state. E-Pass (now Uni) users can get a small rebate on tolls on CFXway roads, but it requires a monthly transaction count of at least 40, so it's effectively only for commuters who drive to and from work 5 days a week.
 
A RR does not just lay ballast then tamp surface and forget it. Trains have to run over it and then any imprefections need surfacing again. The FEC portion can at least have heavy FEC freights but Cocoa to ORL is different.
This is not necessarily as long a process as you make it sound like if done properly during the construction phase. In the distant past settlement of the earthworks, as in the fill could easily be a multi-month to-year or more long process. Proper tamping of the fills as has been done now for 50 plus years essentially reduces this settlement phase to zero. However, do not forget to deal with the underlying soil conditions as the upper zone, particularly given Florida's geography may require removal and recompaction of the top layers of existing soil and installation of sand drains and other forms to reduce settlement of the existing ground due to the superimposed loads. Once this is past, the track portion can go fairly quickly. First, install a good layer of subballast or asphalt base course. Lay out track and ties, add ballast, lift and tamp with multiple cycles. Run a vibrating compactor down the line a couple times. (In years past, multiple passes of your heaviest steam engines did this job.) Run a test train or two. There should be minimal track tweaks needed if the preceding work was done properly. If the tweaks are more than minimal, put that contractor on the never again list. That process may be complex with a government agency, but with a private entity it is very simple. After the fixes, which could be as little as a couple weeks later, run empty trains at increasing speeds until you are comfortable with full speed operation. If all things track are done right, this could just be a few days. Then, invite the politicians along for a joy ride. (Having been involved in one of these it is hilarious to hear some of these people talking about how much pioneers they are to be on the first train over the line.) Now you are ready to go. You might want to run a skeleton service for a few days to a week or so with all station and on board staff but the passengers being limited to other employees and families to enable the operating staff to get familiar with the processes. This last step can go a long way to reducing embarrassment during the first few days of public operation.
 
Based on the LRT lines that I've been involved in, there also is a need for a clearance check with platforms, etc. after the track tamping.

Also, life for Operations and for Customer Service is much better if there are some test runs with the proposed timetable. It may be too late to fix a problem by opening day, but if something unforeseen turns up it's best to not be surprised. This is particularly important on single track lines.
 
Based on the LRT lines that I've been involved in, there also is a need for a clearance check with platforms, etc. after the track tamping.

Also, life for Operations and for Customer Service is much better if there are some test runs with the proposed timetable. It may be too late to fix a problem by opening day, but if something unforeseen turns up it's best to not be surprised. This is particularly important on single track lines.
First para: Which is another good reason for direct fixation, that is a concrete based track form. Can't imagine anyone NOT doing a post-tamping clearance check on ballasted track. Usually just walk your clearance trolley through the platforms. If you have multiple stuff where clearance is an issue, equip a full size car with feeler gauges end car and mid car and run it slowly past the points of concern.

Second paragraph: Yes, for single track lines particularly. Not usually necessary for double track lines unless you have fast trains passing slow trains. Is also a very good idea to check for surprises in the power system. You may not need a full day of this, but you should run loaded trains to check performance under maximum electrical demand.
 
Second paragraph: Yes, for single track lines particularly. Not usually necessary for double track lines unless you have fast trains passing slow trains. Is also a very good idea to check for surprises in the power system. You may not need a full day of this, but you should run loaded trains to check performance under maximum electrical demand.
Absolutely correct. Dispatch systems as well. Any commuter system if it is going to fail will under the most heavily operating conditions. As Brightline increases service each iteration may find gliches.
 
Absolutely correct. Dispatch systems as well. Any commuter system if it is going to fail will under the most heavily operating conditions. As Brightline increases service each iteration may find gliches.
Most of Brightline's traffic will be south of West Palm Beach. For the foreseeable future north of WPB is 1tph each way, or net 2tph. Increase in capacity will be in terms of added cars per consist.
 
Second paragraph: Yes, for single track lines particularly. Not usually necessary for double track lines unless you have fast trains passing slow trains. Is also a very good idea to check for surprises in the power system. You may not need a full day of this, but you should run loaded trains to check performance under maximum electrical demand.
Actually getting a little off topic here mentioning power draw since Brightline will be diesel operated. Sorry about that.

As to platform clearance: The ADA requires a horizontal gap of no more than 3 inches and a vertical difference of no more than 5/8 inches. Many times people have to be reminded that these are legal limits, not design values. My usual has been to go for 2 1/2 inches horizontal and zero vertical. There are those that get nervous about the possibility of the car floor being lower than the platform, so if it makes them feel better go for a platform 1/4 inch lower than the car floor. If on a good concrete track, you could possibly reduce the horizontal to 2 inches but you should not go less due to possible wobbles in the vehicle. In any case, the ends of the platforms should be tapered out in the length beyond the end passenger door to 12 inches or so. Of course if you have curved track through the platforms these conditions cannot be met.

For wider gaps you have to have a bridge plate to use if needed. For low platforms, a lift, etc.
 
Last edited:
I think settlement will always be a potential issue but of course a good contractor knows how to minimize it.
As to platform clearance: The ADA requires a horizontal gap of no more than 3 inches and a vertical difference of no more than 5/8 inches. Many times people have to be reminded that these are legal limits, not design values. My usual has been to go for 2 1/2 inches horizontal and zero vertical. There are those that get nervous about the possibility of the car floor being lower than the platform, so if it makes them feel better go for a platform 1/4 inch lower than the car floor. If on a good concrete track, you could possibly reduce the horizontal to 2 inches but you should not go less due to possible wobbles in the vehicle. In any case, the ends of the platforms should be tapered out in the length beyond the end passenger door to 12 inches or so. Of course if you have curved track through the platforms these conditions cannot be met.
Furthermore the height of the floor above rail can be reduced (minimally) by such things as reduction of wheel diameter through wear and re-profiling, and also the weight of people and baggage on board the train pressing down the suspension.
 
and also the weight of people and baggage on board the train pressing down the suspension.
I don’t know what these particular cars have, but in a properly operating air suspension, leveling valves should automatically compensate for this…
 
Easy enough if you offer a shuttle train MCO-Tampa or MCO-DS.
Sooooo, for whatever reason, the current plans envisage a stub-end station at Disney.

I wouldn't be surprised if Brightline ends up running Orlando Airport - Disney shuttles and a smaller number of Tampa-Disney shuttles, with the regular all-stops trains from Orlando to Tampa skipping Disney.

I know it sounds odd, but... operationally it's going to make sense, and with Disney's "We don't want you to visit anyone else" attitude, forcing customers to backtrack to the airport in order to connect from Disney to I-Drive sounds exactly like what Disney would want.
 
Sooooo, for whatever reason, the current plans envisage a stub-end station at Disney.

I wouldn't be surprised if Brightline ends up running Orlando Airport - Disney shuttles and a smaller number of Tampa-Disney shuttles, with the regular all-stops trains from Orlando to Tampa skipping Disney.

I know it sounds odd, but... operationally it's going to make sense, and with Disney's "We don't want you to visit anyone else" attitude, forcing customers to backtrack to the airport in order to connect from Disney to I-Drive sounds exactly like what Disney would want.
I think Brightline would want to market a single-seat trip between So. FL & WDW. They're in the business of intercity transportation, not shuttling between WDW & OIA.

The stub-end station shouldn't be a problem, since there are locomotives at both ends. It might just require a longer stop to reverse control direction and PTC. I believe that's fairly common in Europe.
 
The stub-end station shouldn't be a problem, since there are locomotives at both ends. It might just require a longer stop to reverse control direction and PTC. I believe that's fairly common in Europe.
Why is a stub end station planned? How do we know that? Is this a done deal?
 
Why is a stub end station planned? How do we know that? Is this a done deal?
Probably set by Disney, to minimize intrusion and the amount of property required. Concept art released a year or 2 ago with a brief description showed it. IIRC, it's also been shown that way in the rough route maps released by Brightline when the route was planned to be along SR 417.

I haven't seen anything saying Disney has bought into the new route since it was moved north to the Sunshine Corridor, stopping at Universal.

I did see one mention of placing the station around S. International Dr., which would be off Disney property, in which case it could be a run-through station. But that might lessen the possibility of Disney participating in last-mile transportation.
 
If the route runs down I-4 by Disney as would be the case with the new proposed alignment, it would be mighty awkward to try to get a stub end station on Disney property. I think that whole thing will be revisited and any siting of station for the 417 alignment is out the window at present. I am sure Disney will not make it difficult for customers to visit Disney, no matter how obtuse they wish to be.
 
If the route runs down I-4 by Disney as would be the case with the new proposed alignment, it would be mighty awkward to try to get a stub end station on Disney property. I think that whole thing will be revisited and any siting of station for the 417 alignment is out the window at present. I am sure Disney will not make it difficult for customers to visit Disney, no matter how obtuse they wish to be.
Not making it difficult, but less likely to provide some sort of shuttle service between the station and Disney's 20 something hotels.
 
Not making it difficult, but less likely to provide some sort of shuttle service between the station and Disney's 20 something hotels.
That would provide a great illustration of the phrase "Cutting ones nose to spite ones face" :D

But then again, it has also gotten out of the business of providing shuttle service from the airport to Disney as I seem to recall. So I suppose it would be par for the course. Brightline would probably cover it with its last mile service anyway, and Sunrail folks would have to fend for themselves.
 