jis
Permanent Way Inspector
Staff member
Administator
Moderator
AU Supporting Member
Gathering Team Member
Al Fazio who was the originally scheduled speaker got held up in meetings at HQ. He was substituted by two speakers - Jim Buechler, Program Director for NEC HSR Program and Theresa Impostato, Director of System Safety, and we got two presentations instead of one.
I. First Jim presented Al's slides, which were substantially the same as presented at TransAction. But off slide in Q&A we got a lot of information about current state which I summarize below:
1. High Speed tests to characterize the behavior of train and track for the purposes of certifying the Acela sets for 160mph commercial operation have been carried out in NJ, DE, MD, MA and RI over the last two weeks. There have been no attempts to create any speed records. It has been a carefully orchestrated set of tests as needed for the certification program.
Two weeks back test were in NJ (County to Ham 160mph), DE/MD (Ragan to Prince 169.2mph). Last week tests were up north and at speed upto 170mph. Last night tests were back in NJ with a goal of upto 170mph. Apparently even though FRA requires 165, Amtrak will be testing upto 170.
2. The new substation at Ham for which design was ready is moving ahead with contract letting this month. Design work on the Adams substation is proceeding. Design work is also going on apace for the Metuchen converter station. Equipment/technology choice will be made in the near future as contracts are finalized.
3. They are facing considerable problem with the "Buy American" stipulation since the following equipment is not manufactured in US any more:
a. High speed catenary cables
b. HV catenary mounting systems
c. High speed switches
d. Frequency Converters
They are trying to work out a combination of special case manufacturing in the US and waivers, both of which are increasing the overall cost of the project and causing potential delays.
4. Track centers will be increased at Delco and Adams to 15' at the interlocking to accommodate high speed crossovers. Track center at Midway will be increased to 13' to accommodate new higher speed crossovers.
5. For electrification some 1200 to 1300 new masts will be installed. All foundation work to be done in 2013, together with some mast installation. A large proportion of them will have solid crossbeams connecting masts on two sides of the RoW to form a solid suspension portal for the OHE. Span length will be some 200' to 230', which is shorter than it is now.. Some existing masts will also be used. 30% of the existing masts require non-trivial foundation repair work. Catenary will look like standard European CT constructions on HSRs, similar to what is found in the new electrification east of New Haven. However, the actual design is in the process of being finalized.
6. 2013 will be mostly foundation prep work and very little track work. Starting 2014, for each construction season of 10 months (2014 - 2017), one track will be taken out of service for the period to upgrade track, do switch replacements and install new catenary, starting with track 1 in 2014. There will be some schedule impact, details of which are being worked now using simulations. There will not be any general service outage through the whole process, and schedule impacts will be kept to a minimum.
II. Then Theresa gave a very comprehensive presentation of how the safety case is being worked to (a) get certification for 160mph operation of Tier II Acelas and (b) work being done towards getting the most out of mixed operation of Tier I, Tier II and Tier III on the NEC. FRA pparently has agree that because of the nature of the NEC, general rules will not apply. There will be special rules specified for the NEC with separate safety case for NEC operations.
1. The basic speed tests will be concluded this year. Early next year they will start full PTC (ACSES + Radio) tests certifying the PTC for 160mph ops.
2. Once that is achieved it is very likely that speeds in MA and RI will be upped to 160 mph sometime in the second half of 2013.
3. MIL-STD-882 is being used for the Hazard Analysis aspect of the Safety Case.
4. There will be no more acquisition of Tier II equipment beyond the proposed 40 car acquisition for Acelas. All further HS acquisition will be Tier III equipment which will be basically off the shelf European (UIC compliant) equipment with very minor modifications for meeting FRA Tier III regs. So odd ly enough Tier III buff strnegth will potentially be less than even Tier I buff strength, but they will have much more sophisticated Crash Energy Management System.
5. The project to allow freight PTC equipped equipment to operate under ACSES based PTC with special radio overlay to interface with them is coming along well.
6. The exact test and certification areas for 160mph at present are:
a. DE/MD Bacon[MP 51.0] - Ragan[MP 29.7]
b. NJ Ham[MP 55.7] - County[MP 32.8]
c. RI MP 151.3 - MP 180.5
d. MA Mansfield [MP 190.5] - Transfer[MP 218.3]
Of these currently there is no funding in place to upgrade catenary in segment (a) above. Segments ( c ) and (d) will get the higher speed as early as late 2013 upon completion of PTC certification. Segment (b) will get it in 2017, upon completion of infrastructure upgrades.
7. Infrastructure upgrades following the same technique as used in the first NJ segment will first be applied to Morris to Holmes (between Trenton and Philly) in PA and County to Lincoln in NJ increasing speed but not necessarily all the way to 160, as funds become available.
8. Tier III specification and operating procedures for NEC development work is proceeding apace. No Tier III equipment can be ordered until this work is completed.
I. First Jim presented Al's slides, which were substantially the same as presented at TransAction. But off slide in Q&A we got a lot of information about current state which I summarize below:
1. High Speed tests to characterize the behavior of train and track for the purposes of certifying the Acela sets for 160mph commercial operation have been carried out in NJ, DE, MD, MA and RI over the last two weeks. There have been no attempts to create any speed records. It has been a carefully orchestrated set of tests as needed for the certification program.
Two weeks back test were in NJ (County to Ham 160mph), DE/MD (Ragan to Prince 169.2mph). Last week tests were up north and at speed upto 170mph. Last night tests were back in NJ with a goal of upto 170mph. Apparently even though FRA requires 165, Amtrak will be testing upto 170.
2. The new substation at Ham for which design was ready is moving ahead with contract letting this month. Design work on the Adams substation is proceeding. Design work is also going on apace for the Metuchen converter station. Equipment/technology choice will be made in the near future as contracts are finalized.
3. They are facing considerable problem with the "Buy American" stipulation since the following equipment is not manufactured in US any more:
a. High speed catenary cables
b. HV catenary mounting systems
c. High speed switches
d. Frequency Converters
They are trying to work out a combination of special case manufacturing in the US and waivers, both of which are increasing the overall cost of the project and causing potential delays.
4. Track centers will be increased at Delco and Adams to 15' at the interlocking to accommodate high speed crossovers. Track center at Midway will be increased to 13' to accommodate new higher speed crossovers.
5. For electrification some 1200 to 1300 new masts will be installed. All foundation work to be done in 2013, together with some mast installation. A large proportion of them will have solid crossbeams connecting masts on two sides of the RoW to form a solid suspension portal for the OHE. Span length will be some 200' to 230', which is shorter than it is now.. Some existing masts will also be used. 30% of the existing masts require non-trivial foundation repair work. Catenary will look like standard European CT constructions on HSRs, similar to what is found in the new electrification east of New Haven. However, the actual design is in the process of being finalized.
6. 2013 will be mostly foundation prep work and very little track work. Starting 2014, for each construction season of 10 months (2014 - 2017), one track will be taken out of service for the period to upgrade track, do switch replacements and install new catenary, starting with track 1 in 2014. There will be some schedule impact, details of which are being worked now using simulations. There will not be any general service outage through the whole process, and schedule impacts will be kept to a minimum.
II. Then Theresa gave a very comprehensive presentation of how the safety case is being worked to (a) get certification for 160mph operation of Tier II Acelas and (b) work being done towards getting the most out of mixed operation of Tier I, Tier II and Tier III on the NEC. FRA pparently has agree that because of the nature of the NEC, general rules will not apply. There will be special rules specified for the NEC with separate safety case for NEC operations.
1. The basic speed tests will be concluded this year. Early next year they will start full PTC (ACSES + Radio) tests certifying the PTC for 160mph ops.
2. Once that is achieved it is very likely that speeds in MA and RI will be upped to 160 mph sometime in the second half of 2013.
3. MIL-STD-882 is being used for the Hazard Analysis aspect of the Safety Case.
4. There will be no more acquisition of Tier II equipment beyond the proposed 40 car acquisition for Acelas. All further HS acquisition will be Tier III equipment which will be basically off the shelf European (UIC compliant) equipment with very minor modifications for meeting FRA Tier III regs. So odd ly enough Tier III buff strnegth will potentially be less than even Tier I buff strength, but they will have much more sophisticated Crash Energy Management System.
5. The project to allow freight PTC equipped equipment to operate under ACSES based PTC with special radio overlay to interface with them is coming along well.
6. The exact test and certification areas for 160mph at present are:
a. DE/MD Bacon[MP 51.0] - Ragan[MP 29.7]
b. NJ Ham[MP 55.7] - County[MP 32.8]
c. RI MP 151.3 - MP 180.5
d. MA Mansfield [MP 190.5] - Transfer[MP 218.3]
Of these currently there is no funding in place to upgrade catenary in segment (a) above. Segments ( c ) and (d) will get the higher speed as early as late 2013 upon completion of PTC certification. Segment (b) will get it in 2017, upon completion of infrastructure upgrades.
7. Infrastructure upgrades following the same technique as used in the first NJ segment will first be applied to Morris to Holmes (between Trenton and Philly) in PA and County to Lincoln in NJ increasing speed but not necessarily all the way to 160, as funds become available.
8. Tier III specification and operating procedures for NEC development work is proceeding apace. No Tier III equipment can be ordered until this work is completed.
Last edited by a moderator: