Single loco ATL to NEC is not a good idea. There are several grades that would slow train too much. And it is more likely that train will be longer than 6 cars.
The wye at 5 points is a problem as 2 legs are used by CSX freights. Ownership of the wye track age is murky and the tails are owned by NS one for sure and 2 by CSX.
What is needed is a joint use agreement to cover both the old Union station / Terminal station area and the parallel 2 main tracks each of CSX / NS to Howell. Provide at least one universal CP thru all 4 main tracks which would allow CSX freights from south to avoid the wye. Also build Howell with flyovers.
But there is not any push to do these items. Now if freight traffic increases ? ? ? ?
Anyone know if the proposed joint dispatch ( NS CSX ) center for the Atlanta area was ever implemented.
The wye at 5 points is a problem as 2 legs are used by CSX freights. Ownership of the wye track age is murky and the tails are owned by NS one for sure and 2 by CSX.
What is needed is a joint use agreement to cover both the old Union station / Terminal station area and the parallel 2 main tracks each of CSX / NS to Howell. Provide at least one universal CP thru all 4 main tracks which would allow CSX freights from south to avoid the wye. Also build Howell with flyovers.
But there is not any push to do these items. Now if freight traffic increases ? ? ? ?
Anyone know if the proposed joint dispatch ( NS CSX ) center for the Atlanta area was ever implemented.
Last edited by a moderator: