neroden
Engineer
So we're still waiting for the all-important second round of testing on the bag-dorms, sleepers, and diners. :-( It's been long enough, you'd think they'd have worked out most of the bugs by now...
They are actually going all the way to left coast. Perhaps someone can send you a picture of the move just in case there are any doubters out there and you can post them...next year!Four new baggage cars from the most recent delivery were released from Hialeah today, heading north on 98(18) to Washington then on to Chicago.
So we're still waiting for the all-important second round of testing on the bag-dorms, sleepers, and diners. :-( It's been long enough, you'd think they'd have worked out most of the bugs by now...
Makes sense, but it has been *14 months*. You can build a prototype of a ground-up design in 14 months!... it really should come out for testing sometime soon...There were a lot of mods.So we're still waiting for the all-important second round of testing on the bag-dorms, sleepers, and diners. :-( It's been long enough, you'd think they'd have worked out most of the bugs by now...
My guess is most of those 14 months, those prototypes have at Elmira doing nothing while the assembly lines were fully setup for the baggage cars.Makes sense, but it has been *14 months*. You can build a prototype of a ground-up design in 14 months!... it really should come out for testing sometime soon...There were a lot of mods.So we're still waiting for the all-important second round of testing on the bag-dorms, sleepers, and diners. :-( It's been long enough, you'd think they'd have worked out most of the bugs by now...
Mmm, that is a possibility. That's a *high risk* possibility, though, because if there *is* a problem with the mods, it means MORE delays. Much better to have done the mods on the prototypes in parallel with the baggage car lines. Requires more workers, however, and I guess CAF might be cheaping out on that.My guess is most of those 14 months, those prototypes have at Elmira doing nothing while the assembly lines were fully setup for the baggage cars.
It's quite possible that they know what mods need to be done and don't feel a need for another round of testing before they start building. And they can't start building until the baggage car lines are done.
Seems like the completion rate of the baggage cars slowed notably after the May delivery. Some sort of stretch-out after they reached 48 or so, iirc. Makes me think perhaps the CAF plant kept one line for the remainder of the baggage cars, and switched to using the other line for other cars, as per the original stated plan. If so, that could mean they're further along with the latest round of mods on diners, sleepers, and bag-dorms than we might think otherwise.Mmm, that is a possibility. That's a *high risk* possibility, though, because if there *is* a problem with the mods, it means MORE delays. Much better to have done the mods on the prototypes in parallel with the baggage car lines. Requires more workers, however, and I guess CAF might be cheaping out on that.My guess is most of those 14 months, those prototypes have at Elmira doing nothing while the assembly lines were fully setup for the baggage cars.
It's quite possible that they know what mods need to be done and don't feel a need for another round of testing before they start building. And they can't start building until the baggage car lines are done.
Not clear to me whether the new baggage car on that was in revenue service or deadheading.This report says the northbound Coast Starlight left Los Angeles today with a new baggage car (plus a private car).
The timing of payments could be a factor, or perhaps was a factor, in the delays.Now that it is a new physical year maybe deliveries of view-2s will accelerate.
Amtrak needs Viewliner II coaches and cafe/lounge cars much worse at this point than additional sleepers. Someone correct me if I'm mistaken, but weren't there only about 85 heritage sleepers circa 1990 (not counting Slumbercoaches); Just ten more than will exist of Viewliner cars shortly.An "extra" $200 million in the budget could make another batch of Viewliner II sleepers look a lot more possible.
Amtrak should order a few hundred single-level coaches, lounges, cafe cars, whatevers. But that's the way to do it, order hundreds at once.Amtrak needs Viewliner II coaches and cafe/lounge cars much worse at this point than additional sleepers.An "extra" $200 million in the budget could make another batch of Viewliner II sleepers look a lot more possible.
...
That is also a strong argument why we need a coach and lounge car order (Amfleet II replacements) sooner rather than later; The 'production line' is open right now. You shouldn't need a prototype since the design is already proven and in production, and a coach is will differ from a sleeper primarily just in interior layout; Structurally they would be essentially the same car. Indeed, keeping the production effort going with a coach order would retain the possibility of ordering additional sleepers down the road.Amtrak should order a few hundred single-level coaches, lounges, cafe cars, whatevers. But that's the way to do it, order hundreds at once.Amtrak needs Viewliner II coaches and cafe/lounge cars much worse at this point than additional sleepers.An "extra" $200 million in the budget could make another batch of Viewliner II sleepers look a lot more possible.
...
At this moment, we can order another 20 or 30 Viewliner II sleepers (or bag-dorms, whatevers) from CAF.
But when CAF's open assembly line closes, this opportunity goes away. In the future, an order for another 20 Viewliner II sleepers would be about like an order for 2 more, with the cost difference between handmade cars and mass production models. So it's now or never for more sleepers.
Going for an order for new single-level coaches, well, lessee. A Request for Proposals, some months pass, bids come in and a winner is picked, a prototype is constructed which may or may NOT pass testing, further delays may ensue, production problems arise, delays may ensue, so deliveries may begin years and years after the decision to order more cars is made.
I feel like I've grown old waiting for the lousy 130-car order from CAF.
But now, we could have another 20 or 30 Viewliner II sleepers in operation within two or three years. Then Amtrak will concentrate on getting the Acela II order right and delivered more or less on time.
Reckon the soonest we get new single-level coaches could be .. well, I won't feel old, I'll be dead and gone.
I watch the CL go by my office window every day and I haven't seen a Heritage baggage car on it for quite a while..It would make logical sense to convert the Coast Starlight next. Currently, Heritage baggage cars are not handled east of Chicago except possibly for DC (there are reports of the Capitol Limited carrying one sometimes) and Hialeah.
Enter your email address to join: